In accordance HEADER - WCT - APRIL2dengan schedule , PT . ACSET INDONUSA foundation work was completed in May 2014 , so that the foundations of the World Capital Tower will be completed on time .
Along with this , the Project Team Pollux Properties is also currently completing drawings for tender purposes , and also has called several leading building material suppliers to ensure the quality of the building World Capital Tower .
Reputable suppliers and have been called one - a time for the presentation of products and can participate in this project . Among others, such as : Schnindler , Kone and Mitsubishi .
In addition , PT . Mega Kuningan Pinnacle has been discussed and met with several prospective main contractor who are all eager to work together on this prestigious project .
Contractors have we invite discussion with , among others : MULTIKON , TOTAL , PP , NKE , ACSET . Of course in the field of contracting , these names are contractors who have working hours , and a lot of achievements . In addition to local contractors , while some foreign contractors who wanted to take part in the World Capital Tower project , among others : POSCO E & C , HYUNDAI , HYUNDAI E & C and also Taisei .