TTJ Holdings

Thread Rating:
  • 0 Vote(s) - 0 Average
  • 1
  • 2
  • 3
  • 4
  • 5
#61
TTJ n Yongnam operates in the same infrastructure biz, most of it is powered by the main client Government, throught SMRT/HDB..etc..
Do look through their both companies presentation slides, they start with forecast of infrastructure spendings till 2015...etc..

Sure, cyclical in a sense, and stable in another sense.. do take a look! Smile
1) Try NOT to LOSE money!
2) Do NOT SELL in BEAR, BUY-BUY-BUY! invest in managements/companies that does the same!
3) CASH in hand is KING in BEAR! 
4) In BULL, SELL-SELL-SELL! 
Reply
#62
(12-07-2013, 10:33 AM)brattzz Wrote: TTJ n Yongnam operates in the same infrastructure biz, most of it is powered by the main client Government, throught SMRT/HDB..etc..
Do look through their both companies presentation slides, they start with forecast of infrastructure spendings till 2015...etc..

Sure, cyclical in a sense, and stable in another sense.. do take a look! Smile

Thanks Brattzz!
Reply
#63
I feel that, TTJ, would be in a good position as our government practices counter-cyclical fiscal policies. There are plenty of opportunities for TTJ to bag new contracts in the near future. Hopefully, there will be involved in the construction of new terminals, etc.

Today, it dropped around by 0.025 before going up by 0.01.
Reply
#64
"THE Downtown MRT Line 2, which will link Singapore's north-western corridor to the new Marina downtown by 2015, is likely to be delayed because a main contractor has gone bust.

Austrian builder Alpine Bau, which was working on the line's King Albert Park, Sixth Avenue and Tan Kah Kee stations, filed for insolvency last week after a failed restructuring plan.

Industry players said the most optimistic outcome would be a six-month slowdown.

"It depends on a number of things," said the managing director of a major construction company. "Like how quickly a receiver is appointed and what it is tasked to do, and if the project is to be re-tendered and how soon that can be done."

The Land Transport Authority (LTA) said there are "legal and contractual matters to be resolved" - a process that it said will take three to six months - before work can resume.

It added that it will work closely with the relevant parties to "minimise the impact" on the project's schedule. But it was unable to say with certainty the likely duration of a delay.

Alpine Bau's plunge into insolvency caught the LTA by surprise.

Its spokesman said yesterday: "Just days before it filed for insolvency, Alpine had given us the assurance and underlined its commitment to complete the station and tunnelling works.

"There had also been no signs of any slowing down of works on site."

The company, which announced its bankruptcy move last Wednesday, has completed about half of the work it set out to do on the three stations and tunnels, said the LTA.

Alpine Bau, owned by Spanish group FCC, won the $670.74 million project in 2009.

Yesterday, it could not be reached for comment at both its Austrian and Singapore offices.

The company, which employs more than 10,000 people worldwide, is Austria's second-largest construction group. It has € 2.56 billion (S$4.3 billion) in debt and equities, reported the Bloomberg news agency, making its insolvency the biggest in Austria since World War II.

According to its website, the company has been trying to restructure its finances for months as it grapples with unprofitable projects in central and eastern Europe.

Up to a day before it announced that insolvency was imminent, the company said its management remained optimistic of a turnaround.

Alpine Bau is relatively new to LTA projects.

Before Downtown Line 2 - part of a three-stage 42km, $21 billion trans-island MRT line - it was involved in building sections of the Circle Line.

The first stage of the underground Downtown Line will link Bugis and Chinatown to Marina Bay.

It is still scheduled to open in the fourth quarter of this year despite a month-long work suspension last year following an accident at Bugis station which killed two workers. "

(29-07-2013, 08:55 PM)kelvesy Wrote: I feel that, TTJ, would be in a good position as our government practices counter-cyclical fiscal policies. There are plenty of opportunities for TTJ to bag new contracts in the near future. Hopefully, there will be involved in the construction of new terminals, etc.

Today, it dropped around by 0.025 before going up by 0.01.

Yes sir! i was trying to grab some at the low but unsucessful!!! #!#@!@#!! some quick eyes and fingers at work!! Tongue

A caretaker contractor will be appointed to ensure safety on a stalled section of the Downtown Line Stage 2 after the main contractor went bust.

A delay in the project and additional costs to complete the project are expected but the extent will be known only after the Land Transport Authority (LTA) makes an assessment in a few weeks, said Transport Minister Lui Tuck Yew in Parliament on Tuesday.

Austrian builder Alpine Bau was working on the line's King Albert Park, Sixth Avenue and Tan Kah Kee stations until it filed for insolvency last month.

Mr Lui assured MPs Sylvia Lim (Aljunied GRC) and Chris De Souza (Holland-Bukit Timah GRC) that the LTA's immediate priority was to ensure the safety and security of the worksites and equipment.

This included securing partially-completed structures, calling in specialists to maintain tunnel boring machines and recharge wells, and ensuring Alpine's workers were properly looked after. - 5th July 2013
1) Try NOT to LOSE money!
2) Do NOT SELL in BEAR, BUY-BUY-BUY! invest in managements/companies that does the same!
3) CASH in hand is KING in BEAR! 
4) In BULL, SELL-SELL-SELL! 
Reply
#65
LTA has appointed McConnell Dowell and SK E&C as the replacement main-contractors to finish off the remaining approx. 50% works of the stalled construction (caused by the sudden insolvency of previous main-contractor Alpine Bau) of the 3 MRT stations of the Downtown Line 2 project along Bukit Timah Road.....
http://app.lta.gov.sg/apps/news/page.asp...40b8c3a721
The total contract sum of the 2 revised contracts amounting to $474.0m, is approx. 71% of the total original contract sum of $670.7m for the 2 original contracts awarded to Alpine Bau, indicating that LTA has to pay approx. $138.0m more for the remaining approx. 50% works to be finished. It looks like the 2 replacement main-contractors and their sub-contractors - including TTJ - stand to make some good money!

TTJ is expected to release its FY13 (ended 31Jul13) full-year results by 31Sep13. Perhaps it is timely to revisit the 1H results.....
http://www.ttj.com.sg/newsroom/yr2013/tt...esults.pdf

I wish for a higher Final dividend than last FY's $0.008/share.
Reply
#66
mot has a lot of money
Reply
#67
(22-09-2013, 09:53 PM)pianist Wrote: mot has a lot of money

guess who's paying the bill? Tongue
1) Try NOT to LOSE money!
2) Do NOT SELL in BEAR, BUY-BUY-BUY! invest in managements/companies that does the same!
3) CASH in hand is KING in BEAR! 
4) In BULL, SELL-SELL-SELL! 
Reply
#68
(23-09-2013, 10:00 AM)brattzz Wrote:
(22-09-2013, 09:53 PM)pianist Wrote: mot has a lot of money
guess who's paying the bill? Tongue
Dun U find the 10% property tax on annual rental value ridiculous even though one is not renting out his house?
Reply
#69
looks like a good company, however current price is not offering any discount.
any chances anyone willing to sell at 24 cents? Tongue
Reply
#70
FY13 (ended 31Jul13) full-year results just out.....
http://infopub.sgx.com/FileOpen/TTJFullY...eID=257645 [results announcement]
http://infopub.sgx.com/FileOpen/TTJFY201...eID=257658 [press release]
http://infopub.sgx.com/FileOpen/TTJFY201...eID=257657 [presentation slides]
While the core Structural Steel division posted a 13.1% YOY fall in Revenue to a still very respectable $111.9m, and a 33.8% YOY fall in PBT to $9.3m (main reason given: the Group completed less work for on-going projects; no mentioning on negative impact from the work delay in 6th Ave and Albert Park Stations on DL2), the Dormitory division posted a small 5.7% YOY increase in Revenue to $15.1m, but a solid 37.5% YOY increase in PBT to $8.3m. The Group generated a rock-solid $22.4m in pretax FCF (or $19.4m in aftertax FCF), and only incurred a smallish $0.3m in net capex in PPE. 31Jul13's net cash balance (inclusive $0.48m in Other Financial Assets) stood at a rock-solid $35.0m, equivalent to $0.10/share (based on the latest 349.8m o/s issued shares). 31Jul13 NAV/share stood at $0.2852. A higher Final dividend of $0.009/share (FY12: $0.008/share) declared, which will be payable on 20Dec13.....
http://infopub.sgx.com/Apps?A=COW_Corpor...&F=1011765
Reply


Forum Jump:


Users browsing this thread: 1 Guest(s)